A2 Second Gotthard tube

Managing the complex material logistics for the construction of the second tunnel

11.01.2024

When the two tunnel boring machines (TBM) for the main tunnel start up at the beginning of 2025, the materials management will also go into full operation. In the video, civil engineer Tobias Griessmair explains the challenge of transporting 7.4 million tons of rock.

Around 7.4 million tons of rock will be excavated to build the second Gotthard tunnel. A large proportion of this will be reused – among other things for tunnel construction and the renovation of the first tube.

The excavated material is categorized in the tunnel and then transported to the surface. Almost all of the material is then transported to the processing plant on the south side via conveyor belts and through the Gotthard rail tunnel.

20230404 0017 2tg gotthard foto goeschenen vlr seeschuettung
20231107 13 2tg gottardo foto airolo ndi nastro traspoprto materiale
20231107 01 2tg gottardo foto airolo ndi nastro traspoprto materiale
20230921 1031 2tg gotthard foto goeschenen dsr uebersicht drohne
20230524 037 2tg gottardo foto airolo ndi Area Lotto 341
20230921 1055 2tg gotthard foto goeschenen dsr kaverne

Concrete cavern in Göschenen

Due to the limited space available in the Urner Reusstal, an additional cavern was excavated in Göschenen, where the underground concrete plant is currently being installed.