A2 Second Gotthard tube

The construction of the second tube will take a total of ten years. The renovation of the existing tunnel will then take around another three years. From 2033, traffic will pass through both tunnels, with each tunnel having a single lane and its own hard shoulder.

2033

  • End of renovation work on the first Gotthard road tunnel
  • Rennovation of the first tube
     

2030

  • System tests and commissioning of the entire system
  • Opening of the second Gotthard road tunnel

2028

  • Operating and safety equipment

2027

  • Breakthrough for the main tunnel
  • Construction of the second tube 

2025

  • Excavation with tunnel boring machines (TBM) from the north and south

2022

  • Start of the construction of the main tunnel
  • Commencement of excavation using tunnel boring machines (TBM) for the northern and southern access tunnels

2021

  • Start of construction work for the re-routing of the service and infrastructure tunnel
  • Start of construction work for the northern and southern access tunnel

2020

  • General start of construction work in Göschenen and Airolo