A2 Second Gotthard tube

Tunneling methods

The 16.9 kilometre-long second tube will be almost entirely excavated using two tunnel boring machines (TBM). Blasting is only necessary in the two geological fault zones and around the portals. Two further tunnelling machines were used to excavate tunnels to access the fault zones.

The tunnel boring machines

Two single-shield TBMs are in operation in the main tunnel. In shield tunnelling, precast ring-shaped lining segments (Tübbing) are installed to prop up the excavated tunnel. Hydraulic thrust cylinders advance the TBMs 10 metres at a time. The TBMs have a diameter of about 12.3 metres. At up to 4.6 revolutions per minute, they have an average drilling performance of two metres per hour.

The tunnelling machines are mounted at the respective portals and positioned in pre-excavated start tubes. After the breakthrough, the TBMs will be dismantled and removed.

Smaller TBMs with a diameter of around 7.4 metres have already been used to create the tunnels to access the two geological fault zones. A single-shield TBM was used at the southern end of the tunnel and a gripper TBM at the northern end. Unlike the shield TBM, a gripper TBM does not require Tübbing elements. Instead, the tunnel wall is secured with shotcrete (sprayed concrete), which is why a gripper TBM is only used in very stable rock.

More about the TBMs:

 TBM north main tunnelTBM south main tunnelTBM north access tunnelTBM south access tunnel
Construction lot241341243343
NameAlessandraPaulinaCarlaDelia
TypeSingle-shield TBMsSingle-shield TBMsGripper TBMsSingle-shield TBMs
Advance6'885 m7'750 m3'940 m5'000 m
Period of use2025 – 20272025 – 20272022 – 20232022 - 2023
Front plate diameter12,225 m12,310 m7,030 m7,400 m
LengthCa. 110 mCa. 110 mCa. 200 mCa. 175 m
Weight1806 t2118 t2000 t1110 t
Power unit5250 kW (7138 hp), 15 electric motors, each with 350 kW5600 kW (7613 hp), 16 electric motors, each with 350 kW2800 kW (3807 hp)2800 kW (3807 hp)
Moment of force26 767 kNm28 552 kNm4408 kNm4375 kNm
ProducerHerrenknecht AG, Schwanau (Deutschland)Herrenknecht AG, Schwanau (Deutschland)Herrenknecht AG, Schwanau (Deutschland)Herrenknecht AG, Schwanau (Deutschland)
Construction companyARGE secondo tubo: Implenia Schweiz AG, Frutiger AGConsorzio Gottardo Süd: Marti Tunnel AG, Mancini & Marti SA, Ennio Ferrari SAARGE secondo tubo: Implenia Schweiz AG, webuild S.p.A, csc costruzioni sa, Frutiger AGConsorzio Marti 2TG Lotto 343: Marti Tunnel AG, Mancini & Marti SA, Ennio Ferrari SA

BLASTING IN THE FAULT ZONES

There are two fault zones to the north and south of the tunnel which affect the construction work: the approx. 270-metre long Mesozoic fault zone around 4.1 kilometres after the Göschenen portal, and the almost 300-metre long Guspis fault zone, which is around 4.9 kilometres after the Airolo portal. Pressurised rock conditions prevail in each of these fault zones, so they are being excavated using conventional means rather than using a TBM. Some areas of unconsolidated rock have to be worked on with a pick hammer and excavator shovel and immediately secured with shotcrete and anchors. Steel arches also ensure that the pressure from the rock does not reduce the size of the tunnel cross-section to any significant extent. More compact rock sections are excavated by blasting.